Development pipeline Whitemarsh Township Corson Tract
Whitemarsh's planning report puts the rehabilitation of the Abolition Hall buildings at $5.7 million to $7.1 million over two phases
Mark B. Thompson Associates priced the first phase at $905,000 to $1.1 million, targeted for fall 2026 through 2027. The second, $4.8 million to $6 million, is targeted for 2028 or 2029 and depends on a capital campaign.
Rough order of magnitude construction cost by phase, in dollars. The solid bar runs to the low estimate and the open box to the high one. The combined range adds the two phase totals and leaves out the start-up work and the interim caretaker's quarters, which the report lists as township budget with no amount. Source: Corson Tract Assessment and Preliminary Planning Report, June 17, 2026, Whitemarsh Township, checked October 26, 2026.
Whitemarsh Township's architect for the Corson Tract, Mark B. Thompson Associates, puts the cost of turning the tract's three historic buildings from houses into public program space at $5.7 million to $7.1 million, in two phases of construction. The figures come from the firm's Assessment and Preliminary Planning Report, dated June 17, 2026, which the township attached to the agenda for the October 27 meeting of its Abolition Hall Steering Committee. The first phase, $905,000 to $1.1 million plus items the township would handle itself, carries a target schedule of fall 2026 through 2027. The second, $4.8 million to $6 million, is targeted for 2028 or 2029 and depends on a capital campaign.
The same agenda lists an update on a bid approval for invasive species removal, naming Stonewood Landshaping, Inc. and a $174,100 project, and a request to apply for a 2026 LSA grant, as the agenda names it, for some of the building and property improvements the report lays out.
The Corson Tract is 10.45 acres at Butler Pike and Germantown Pike in Plymouth Meeting, inside Whitemarsh. The township bought it in 2022 with the Whitemarsh Art Center, with support from the Karabots Foundation, and became sole owner in 2025, the report says. It holds the Hovenden House, the Maulsby Barn and Abolition Hall, where, according to the report, the Corson family hosted antislavery speakers before the Civil War.
The estimate by phase
Every first-phase line tops out at $500,000 or less
The report gives each piece of work a rough order of magnitude range, an early budgeting number set before any design or cost estimate. The first-phase lines depend on available funding, the report says. Envelope repairs and the Hovenden House apartment are marked “contractor proposals to be solicited.”
Rough order of magnitude construction cost for each priced line, in dollars, grouped by target schedule, all on one scale. Phase 1B, the interim caretaker's quarters, and the start-up work are listed as township budget, amount to be determined, and are not shown. Source: Corson Tract Assessment and Preliminary Planning Report, June 17, 2026, Whitemarsh Township, checked October 26, 2026.
The first phase covers exterior envelope work on all three buildings: prioritized masonry and exterior wood repairs, chimney repairs and moisture control in the Hovenden House basement, and the structural engineering analyses the assessment recommends. Site work along Butler Pike would add a curb cut, a driveway and parking that start as gravel subbase for later paving, drainage, lighting, a meadow trail and accessible walkways. The tree line covers removal of invasive trees and reforestation. The Hovenden House second floor would become a caretaker's apartment, with remediation for moisture and radon, kitchen and bathroom work, window repair or replacement and a code-compliant egress system.
The second phase covers the rest of the rehabilitation. It adds a 300-square-foot accessible entry to the meadow side of the Maulsby Barn and a 1,000-square-foot courtyard addition with an elevator between the barn and Abolition Hall, and it rebuilds the hall's north balcony as a second means of egress. The report puts the second phase at about 8,000 square feet.
What the code review found
All three buildings are classed R-3 today, and the plans need a change of use
All three buildings are classed today as R-3, a residential occupancy. The report expects the township's plans to need a change of use, which under the International Existing Building Code that Pennsylvania's Uniform Construction Code adopts brings stricter requirements than an alteration within the same use. The proposed classifications are B and R-3 for the house and barn, and A-3, an assembly group, and B for the hall.
Approximate existing floor area of each building in square feet, drawn as squares whose area is to scale; open squares are the proposed additions. Occupancy groups under the International Existing Building Code. Source: Corson Tract Assessment and Preliminary Planning Report, June 17, 2026, Whitemarsh Township, checked October 26, 2026.
| Building | Existing area (sq ft) | Occupancy today | Proposed occupancy | Sprinklers proposed |
|---|---|---|---|---|
| Hovenden House | 5,790 | R-3 | B / R-3 | Required by R-3 (NFPA 13D permitted) |
| Maulsby Barn | 4,410 | R-3 | B / R-3 | Required by R-3 (NFPA 13D permitted) |
| Abolition Hall | 1,850 | R-3 | A-3 / B | Required by A-3 |
The report describes all three as Type III-B construction, with masonry bearing walls and wood interior framing. None has sprinklers or a fire alarm. It expects any major renovation to replace HVAC, electrical and plumbing in full and to add sprinklers, monitored alarms, exit signs and emergency lighting, concealed without harm to historic fabric. Most occupancies would need two separated means of egress from each floor.
The report lists what earlier surveys and the 2025-2026 site visits found.
Hazardous materials, utilities and building conditions
- Asbestos
- Transite wall panels and shingles on the siding of Maulsby Barn and Abolition Hall, and flooring in a second-floor bathroom of Maulsby Barn; removal by a Pennsylvania-licensed abatement contractor before work disturbs them
- Lead-based paint
- Found throughout the property; work that disturbs it should use lead-safe practices by certified individuals working for a certified firm
- Radon
- Screening results between 4 and 10 pCi/L in Hovenden House, with reduction recommended; below 4 pCi/L in Maulsby Barn and Abolition Hall
- Septic
- Three historic private septic systems, to be abandoned under applicable rules if that has not been done
- Water service
- A 2-inch combined domestic and fire service sized per NFPA 13 to each of the two building locations
- Electric service
- Three-phase service if available, with a pad-mounted transformer; location pending discussion with PECO
- Sanitary and storm lines
- Jet and scope to verify integrity; replacement may be needed depending on results
- Building systems
- Any major renovation expected to replace HVAC, electrical and plumbing in their entirety and add sprinklers, alarms, exit signs and emergency lighting
- Structure
- Repairs expected to roof framing, floor framing, lintels and stone masonry, with structural analysis based on the proposed uses
Source: Corson Tract Assessment and Preliminary Planning Report, June 17, 2026, Whitemarsh Township, checked October 26, 2026.
Review and funding
The largest grant application, $250,000 for parking and trails, was pending in June
The tract sits in the Plymouth Meeting Historic District, so exterior work visible from a public way goes before the joint Historical Architectural Review Board of Plymouth and Whitemarsh, which uses the Secretary of the Interior's Standards for Rehabilitation. The report recommends consulting the board early. It says the property, in the VC-2 Village Commercial district, is understood to be exempt from the zoning ordinance because the township owns and operates it.
At the committee's June 25 meeting, the township manager reported on three grant applications. The minutes say the Greenways, Trails and Recreation grant would pay for parking and trails across the site and requires a 20% match, stated as $65,000, from the Open Space Fund.
Grant amount applied for, in dollars, and its status as reported at the Abolition Hall Steering Committee's June 25, 2026 meeting. Source: Steering committee minutes, June 25, 2026, Whitemarsh Township, checked October 26, 2026.
What this means for contractors
Every priced line is above the $25,000 prevailing wage threshold
The report says near-term work needing specialized skills would go out through targeted requests for proposals to qualified specialty trade and restoration contractors, and that the larger rehabilitation would come in phased projects. The first-phase scopes call for masonry, exterior carpentry, chimney, window, site and environmental remediation work. Watch the Abolition Hall Steering Committee and Board of Supervisors agendas in the township's Agenda Center, and see the public bids guide for where township bids are advertised.
First-phase lines, rough order of magnitude cost in dollars, against the threshold the Department of Labor and Industry gives for building construction with public funds. Sources: Corson Tract Assessment and Preliminary Planning Report, June 17, 2026, Whitemarsh Township, checked October 26, 2026. Prevailing Wage Projects, Pennsylvania Department of Labor and Industry, checked October 26, 2026.
The Department of Labor and Industry says prevailing wage applies to building construction projects of $25,000 or more when public funds are involved, and a project may not be split into pieces to fall below that line. Every priced line in the report exceeds that amount. The prevailing wage guide covers rate requests and certified payroll.
Before pricing an exterior scope, ask the township whether the review board has issued a certificate of appropriateness for it.
Caveats
The ranges are early budgeting figures, set before design
The ranges are early budgeting figures. The report says professional construction cost consulting was not part of the study and that cost estimating will be needed as projects are defined. The second-phase dates and escalation are listed as to be determined. The $5.7 million to $7.1 million combined range adds the two phase totals and leaves out start-up work and the interim caretaker's quarters, which the report lists as township budget with no amount. Whether the committee or the Board of Supervisors acted on the invasive removal bid or the grant request could not be verified, because the October 27 meeting had not taken place when this was checked on October 26, 2026.
The data
Seven priced lines, from $50,000 to $3,100,000
| Phase | Work | Target schedule | Low estimate | High estimate | Range on one scale |
|---|---|---|---|---|---|
| 1A | Exterior envelope repairs on all three buildings | Fall 2026 to spring 2027 | $150,000 | $200,000 | |
| 1C | Site work along Butler Pike: curb cut, driveway, parking, drainage, lighting and paths | Fall 2026 to spring 2027 | $450,000 | $500,000 | |
| 1C | Tree restoration: removal of invasive trees and reforestation | Fall 2026 to spring 2027 | $255,000 | $300,000 | |
| 1D | Hovenden House second floor caretaker's apartment | Fall 2027 | $50,000 | $100,000 | |
| 2A | Hovenden House first floor and exterior envelope | 2028 or 2029 | $600,000 | $800,000 | |
| 2B, 2C | Maulsby Barn ground floor with 300 sq ft entry addition and Abolition Hall ground floor | 2028 or 2029 | $1,600,000 | $2,100,000 | |
| 2D | Maulsby Barn and Abolition Hall main floors with 1000 sq ft elevator addition | 2028 or 2029 | $2,600,000 | $3,100,000 |
Source: Corson Tract Assessment and Preliminary Planning Report, June 17, 2026, Whitemarsh Township, checked October 26, 2026. Download the data (CSV)