Solicitation 6609Montgomery County Dept. of A&IUpper Moreland Township
Montgomery County's Willow Grove Annex renovation goes to bid in five prime contracts, each under its 70% apprenticeship rule
Bids for the county's gut renovation of the annex are due November 19. Every prime contractor and every subcontractor on the job signs the county's responsible contractor certification, and at least 70% of craft labor hours must be worked by registered apprentices or by graduates of registered programs.
- Bids due
- Nov 191:00 p.m., on Bonfire
- Questions due
- Nov 61:00 p.m.
- Prime contracts
- 5Each with its own bid form
- Policy threshold
- $250,000County projects at or above
- Scale
- NTS
- Dwg no.
- montgomery-county-willow-grove-annex-bid-2026-10
Shares of all craft labor hours on the project, as the county's procurement policy, amended June 11, 2026, sets them. Source: Montgomery County procurement policy, sections 6(c)(12) and 6(c)(13).
Montgomery County is taking bids through November 19, 2026 to renovate its Willow Grove Annex at 102 North York Road in Upper Moreland Township, and the job is split into five prime contracts: general, mechanical and HVAC, electrical, plumbing and fire protection. The invitation went up on the county's Bonfire portal on October 6. Each prime must file the county's responsible contractor certification, and the county's procurement policy requires that at least 70% of the craft labor hours on a project of this kind be worked by graduates of registered apprenticeship programs or by registered apprentices. Bids are due at 1:00 p.m. on November 19, and questions at 1:00 p.m. on November 6.
01The county split the gut renovation into five prime contracts
The county's 2026 budget lists the job for its capital projects staff as the start of the annex building's "gut rehabilitation." The commissioners' June 11, 2026 agenda listed the solicitation, describing it as "full renovation construction services" paid from capital funds. In 2023, when the commissioners approved design work on the building, The Reporter quoted commissioners' chairman Ken Lawrence Jr. as saying it provides services such as the county's community connections departments.
| Tag | Prime contract | Bid form | Base bid table | Also requires |
|---|---|---|---|---|
| GC | General contracting | GC Bid Form | General Contractor (Base Bid) | Alternates and unit prices table |
| MC | Mechanical and HVAC contracting | MC Bid Form | Mechanical/HVAC Contractor (Base Bid) | |
| EC | Electrical contracting | EC Bid Form | Electrical Contractor (Base Bid) | |
| PC | Plumbing contracting | PC Bid Form | Plumbing Contractor (Base Bid) | |
| FPC | Fire protection contracting | FPC Bid Form | Fire Protection Contractor (Base Bid) |
Forms listed on the public bid page for solicitation 6609, checked October 30, 2026. Source: Montgomery County Bonfire portal. Download the data (CSV)
The portal lists a bid form and a base bid table for each prime. The general contractor also prices alternates and unit prices. The drawing sets posted with the invitation are labeled architectural, civil, structural, mechanical, electrical and PFP, and they come with a specification book, a hazardous building material evaluation, a site logistics plan, a bid schedule and a prevailing wage rate sheet dated October 5, 2026.
- Architectural
- Civil
- Structural
- Mechanical
- Electrical
- PFP
Anyone can read the listing, but downloading the documents and bidding takes a free Bonfire account, as the county's procurement page explains.
02Bids are due at 1:00 p.m. on November 19, after two mandatory pre-bid meetings
The county held a mandatory pre-bid meeting at the annex on October 13. On October 15 it posted a notice that it had extended the question and bid due dates. On October 22 it added a second mandatory pre-bid meeting, held October 27, for firms that missed the first, and posted an updated bid schedule.
| Date, 2026 | Step | Where |
|---|---|---|
| October 6 | Invitation to bid opens on Bonfire | Online portal |
| October 13 | Mandatory pre-bid meeting | Willow Grove Annex, 102 N. York Road |
| October 15 | County notice extends the question and bid due dates | Online portal |
| October 22 | County schedules a second mandatory pre-bid meeting and posts an updated bid schedule | Online portal |
| October 27 | Second mandatory pre-bid meeting for firms that missed the first | Willow Grove Annex, 102 N. York Road |
| November 6 | Questions due by 1:00 p.m. | Online portal |
| November 19 | Bids due by 1:00 p.m. | Online portal |
Dates as posted on the bid page and in the county's notices, checked October 30, 2026; they can change by addendum. Source: Montgomery County Bonfire portal. Download the data (CSV)
By October 29 the portal showed 95 public questions from prospective bidders, with one marked answered and the rest in review. They include questions on which prime removes the electrical service and in-building transformers, and on whether to price unsampled tile grout and leveling compound as asbestos-containing.
03The county's rules reach every contractor and subcontractor on projects of $250,000 or more
The county's procurement policy, as amended June 11, 2026, applies its responsible contractor requirements to county construction, demolition, alteration, renovation and maintenance projects valued at $250,000 or more, and to every contractor and subcontractor of any tier on them. The bid lists the county's responsible contracting packet, dated June 15, 2026, and a signed responsible contractor certification for each prime contract.
The certification commits the firm to take part in a registered apprenticeship program for each trade it employs. The program has to be registered with the U.S. Department of Labor or a state apprenticeship agency and must have graduated apprentices to journeyperson status in at least three of the past five years. At least 70% of craft labor hours must be worked by those graduates or by registered apprentices, in the ratio the table shows. The firm also commits to a good-faith effort to fill at least 40% of craft labor hours with Montgomery County residents, and to report each nonsupervisory worker's ZIP code and apprenticeship status on its payroll reports.
Registered apprentices per crew under the ratio in section 6(c)(12) of the county's procurement policy, amended June 11, 2026, drawn for a range of crew sizes. Source: Montgomery County procurement policy.
| Note | Requirement | What the county policy says | Section |
|---|---|---|---|
| 1 | Which projects | County construction, demolition, alteration, renovation or maintenance projects valued at $250,000 or more | 5(b) |
| 2 | Who it covers | Every contractor and subcontractor of any tier on those projects | 5(b) |
| 3 | Certification | Each prime submits a Contractor Responsibility Certification, signed under penalty of perjury; a bid without one is disqualified | 6(a) and 6(g) |
| 4 | Apprenticeship program | For each trade it employs, the firm takes part in a registered apprenticeship program that has graduated apprentices to journeyperson in at least 3 of the past 5 years | 6(c)(11) |
| 5 | Apprentice-trained labor | At least 70% of craft labor hours by graduates of such programs or by registered apprentices | 6(c)(12) |
| 6 | Apprentice ratio | 1 apprentice for 1 to 4 journeypersons, 2 for 5 to 9, and 1 more for each further 5 | 6(c)(12) |
| 7 | County residents | Good-faith effort to fill at least 40% of craft labor hours with Montgomery County residents | 6(c)(13) |
| 8 | Payroll reports | Each nonsupervisory worker's ZIP code and whether the worker is a registered apprentice or a program graduate | 6(c)(14) |
| 9 | Safety training | OSHA 10-hour course for all craft labor before work starts, and one person on site with the OSHA 30-hour course for a prime | 6(c)(10) |
| 10 | Subcontractors | Subcontractor list and subcontractor certifications due within 2 days of the notice to proceed | 8(a) |
| 11 | Protests | Within 7 days of the later of the final responsibility determination or the notice of intent to award on Bonfire | 25(b) |
Paraphrased from the policy as amended June 11, 2026, checked October 30, 2026. The CSV download adds the policy's look-back rules on a firm's record, sections 6(c)(3) to 6(c)(7). Source: Montgomery County procurement policy. Download the data (CSV)
04Subcontractor certifications are due 2 days after the notice to proceed
Award takes several steps after bids open. The county first issues a notice of intent to award, then reviews the firm's certification and its subcontractors' before it issues a written responsibility determination.
- Bids dueNovember 19, 1:00 p.m.
- Notice of intent to awardPosted on Bonfire
- Responsibility determinationWritten, after the county reviews the certifications
- Notice to proceedSubcontractor list and certifications due within 2 days
The awardee has two days from the notice to proceed to submit its subcontractor list with a certification from each subcontractor, and the policy bars any subcontractor that is not on the list. The county posts the certifications, the subcontractor lists and its determination on its website for the length of the contract.
Whitemarsh Township is weighing similar rules for its own public work. See Whitemarsh's draft contractor ordinance.
05The design contract stands at $1,078,400.36 after two amendments in 2026
The commissioners' April 9 and June 11, 2026 agendas each carry an amendment to the county's architectural and engineering contract with NORR Design for the annex. The April amendment added $45,125.36, bringing it from $987,675 to $1,032,800.36, and the agenda gives the reason as drawing and design changes for the building code update. The county's agenda says Pennsylvania adopted the 2021 International Code Council codes as of January 1, 2026, with their use required as of July 1, 2026. The June amendment added $45,600 for scope changes, bringing the contract to $1,078,400.36.
| Step | Date | Change | Contract amount | Reason given |
|---|---|---|---|---|
| Award to NORR for architectural and engineering services | June 2023 | $721,215.00 | Original agreement as reported by The Reporter | |
| Amount in force after an October 23, 2025 resolution | October 23, 2025 | $987,675.00 | Amount listed as the prior contract amount in April 2026 | |
| Amendment | April 9, 2026 | $45,125.36 | $1,032,800.36 | Drawing and design changes for the 2021 ICC code update |
| Amendment | June 11, 2026 | $45,600.00 | $1,078,400.36 | Scope changes |
Contract amounts in dollars. How the contract grew between the first two amounts could not be verified. Sources: the commissioners' April 9, 2026 and June 11, 2026 agendas; the 2023 amount from The Reporter. Download the data (CSV)
The Reporter put the original 2023 agreement at $721,215, which makes the current amount 49.5% higher. How the contract grew between 2023 and an October 23, 2025 resolution could not be verified.
The April agenda also extends the county's owner-controlled insurance program, or OCIP, to the "Willow Grove Building Improvements," Phase 3 of the Montgomery County Justice Center and the Montco-Norristown Public Library. The bid listing includes an OCIP 2 document.
06What to line up before November 19
Gather the apprenticeship paperwork for each trade you will self-perform. The certification asks for a list of those trades, documents that give each program's name, state and registration number, and copies of your workers' apprenticeship credentials. Collect the same from every subcontractor you plan to carry. Their certifications are due two days after the notice to proceed, and the county can disqualify a subcontractor that does not meet the policy.
Read the OCIP document against your own insurance before you price. If it is unclear which coverages to leave out of your number, ask through the portal before the November 6 question deadline.
Pennsylvania's prevailing wage rules apply to this job, and the county posted the rate sheet with the bid. The governor approved Senate Bill 908, which amends the Prevailing Wage Act, on October 22, 2026 as Act 101 of 2026, according to the General Assembly's bill page. Ask the county whether it applies to fabricated items on this job. See the House vote on the bill for what it covers, and where public construction bids are posted and how the Prevailing Wage Act applies for background.
Caveats
The bid documents sit behind a Bonfire login, so this article draws on the public listing, the county's policy and the commissioners' agendas. The construction estimate and the completion date could not be verified from those pages. A bidder's question asking for the general contract budget was still in review on October 29.
The bid dates were extended once and could move again in an addendum, so check the listing before you submit.
The policy's $250,000 threshold can be raised for inflation by the county's chief financial officer, who posts any change on the purchasing page. The policy also lets the county waive the responsible contractor requirements for a sole bidder that does not meet them, or reissue a solicitation with a waiver when no bids arrive. For how the certification applies to your firm, ask the county's Office of Procurement through the portal or your own attorney.