Borough bidsConshohocken BoroughPennBid opportunity 261356

Conshohocken's public safety building at 1111 Fayette Street goes to bid in five prime contracts, with bids due December 9

Conshohocken is taking bids through December 9 on five prime contracts for its Fayette Street public safety building, with a mandatory pre-bid on November 9.

Sealed bids due

December 9

2:00 p.m., opened in public at Borough Hall, 400 Fayette Street

Prime contracts
5General, HVAC, electrical, plumbing, traffic signal
Mandatory pre-bid
Nov 92:00 p.m., after a site walk from 10:00 a.m.
Questions due
Dec 24:00 p.m. on PennBid
Bid security
10%Of the base bid, for each contract bid

Bids open December 9, and Act 101 takes effect December 21

BID PERIOD ON PENNBIDNov 2Nov 9Nov 16Nov 23Nov 30Dec 7Dec 14Dec 21Dec 28NOVEMBER 2026DECEMBER 2026NOV 3Documents posted on PennBidNOV 9Site walk 10 a.m. to 2 p.m.Mandatory pre-bid at 2 p.m.DEC 2Questions due on PennBidby 4 p.m.DEC 9, 2 P.M.Bids due and opened at Borough HallDEC 11Original bid documents fromthe three lowest biddersDEC 21Act 101 takes effect Nov 2Nov 9Nov 16Nov 23Nov 30Dec 7Dec 14Dec 21Dec 28NOV 3Documents posted on PennBidNOV 9Site walk 10 a.m. to 2 p.m.Mandatory pre-bid at 2 p.m.DEC 2Questions due on PennBidby 4 p.m.DEC 9, 2 P.M.Bids due and openedat Borough HallDEC 11Original bid documents fromthe three lowest biddersDEC 21Act 101 takes effect
Dates of the bid from November 1 to December 31, 2026. The shaded band runs from the November 3 posting to the December 9 deadline. Sources: Borough of Conshohocken bid notice, PennBid listing and the text of Senate Bill 908, all checked November 5, 2026. Addenda can change the dates.

Conshohocken Borough is taking sealed bids through 2:00 p.m. on Wednesday, December 9, 2026 to build its new Public Safety Facility at 1111 Fayette Street, the fire and EMS building it has been planning since early 2025. The work is split into five prime contracts: general, HVAC, electrical, plumbing and traffic signal modernization.

The borough posted the notice on November 3, the same day the specifications and drawings went up on PennBid at no cost. Every prime bidder must attend a pre-bid meeting at Borough Hall at 2:00 p.m. on Monday, November 9, and the borough calls it mandatory. The job is covered by the Pennsylvania Prevailing Wage Act.

What is out to bid

Five prime contracts, each with its own submission and pricing table on PennBid

The notice lists five prime contracts, and PennBid takes a separate submission and pricing table for each. PennBid names Contract No. 2 "Mechanical Construction," while the borough's notice calls it HVAC Construction. Bidders say which primes they intend to bid when they register on PennBid.

Contract No. 2 goes by two names, and three of the five cover trades that Act 101 names

  1. Contract No. 1

    General

    BT-14NU

  2. Contract No. 2

    HVAC

    PennBid: Mechanical Construction

    BT-07NO

    Trades Act 101 names

  3. Contract No. 3

    Electrical

    BT-48KY

    Trades Act 101 names

  4. Contract No. 4

    Plumbing

    BT-48IV

    Trades Act 101 names

  5. Contract No. 5

    Traffic Signal Modernization

    BT-78ET

The five prime contracts as the borough's notice names them, with the PennBid submission name where it differs and the PennBid pricing table code. Sources: bid notice and PennBid listing, checked November 5, 2026. The Act 101 marks follow the article's reading of the act.

The posted package has two files, a specification book and a bid drawing set, both under the architect's project number 25-061. The architect is Alloy5 Architecture of Bethlehem. PennBid lists the job as an invitation for bids on a fixed fee contract. Reading the listing takes no account, but downloading the files and submitting a bid takes a free PennBid supplier account.

The schedule

Bids open in public at Borough Hall right after the 2:00 p.m. deadline on December 9

The site at 1111 Fayette Street is open for a walk-through by bidders, subcontractors and vendors from 10:00 a.m. to 2:00 p.m. on November 9, ahead of the pre-bid meeting. Questions are due on PennBid by 4:00 p.m. on December 2. Bids open in public at Borough Hall, 400 Fayette Street, right after the December 9 deadline, and PennBid will post the results. The notice says the borough will award the contracts "at a later date" and gives no award or construction schedule.

The borough asked for architects in March 2025 and set the bid deadline for December 9, 2026

MarAprJulOctJanAprJulOct20252026BID PERIOD NOV 3 TO DEC 9MAR 21, 2025Borough asks architects for proposalsDEC 2025Cleanup plan sent to DEPOCT 7Alloy5 update, waiver of landdevelopment review on agendaOCT 21Bond ordinance and bid ad on agendaOCT 22Governor approves Act 101 MarAprJulOct2026AprJulOctMAR 21, 2025Architect proposals requestedDEC 2025Cleanup plan sent to DEPOCT 7Alloy5 update on agendaOCT 21Bonds and bid ad on agendaOCT 22Governor approves Act 101NOV 3Bid documents postedDEC 9Bids due and openedDEC 21Act 101 takes effect
Steps toward the bid from March 2025 to December 2026, placed by date. The December 2025 date is approximate. Sources: borough notices on the architect search and the cleanup plan, council agendas for October 7 and October 21, 2026, and the General Assembly bill page, checked November 5, 2026.

In March 2025 the borough asked for proposals from architects with fire and EMS facility experience for the building at 1111 Fayette Street. In December 2025 it told the public it had sent the state Department of Environmental Protection a remedial investigation report and cleanup plan for the former EF Moore Chevrolet property at 1109-1119 Fayette Street and 1201 Butler Pike in Whitemarsh Township. The October 7, 2026 council work session listed an update from Alloy5 and Resolution 2026-15, which would waive subdivision and land development review for the building.

On October 21, council's agenda carried both Ordinance 2026-03, on bonds of up to $15 million, and a motion to authorize the bid advertisement. The bond notice lists the development and design of a new public safety facility as the first of five purposes, alongside roads, a public works property, fire and EMS vehicles and the cost of issuing the bonds. The October 10 article on the bond ordinance covers its limits and repayment schedule.

How the building reached bid, and the dates ahead
DateStepSource
Mar 21, 2025Borough asks for architects' proposals for a fire and EMS building at 1111 Fayette Street (due April 24 2025)Borough RFP notice
Dec 19, 2025Borough submits a remedial investigation report and cleanup plan for the former EF Moore Chevrolet site to the state Department of Environmental Protection (approximate date)Borough notice
Oct 7, 2026Council work session lists an Alloy5 update and Resolution 2026-15 waiving land development review for the buildingCouncil agenda
Oct 21, 2026Council agenda lists Ordinance 2026-03 on up to $15 million in bonds and authorizing the bid advertisementCouncil agenda and bond notice
Oct 22, 2026Governor approves Senate Bill 908 as Act 101 of 2026General Assembly bill page
Nov 3, 2026Bid documents posted on PennBid at no costBid notice and PennBid listing
Nov 9, 2026Site walk-through from 10 a.m. to 2 p.m. and mandatory pre-bid meeting at 2 p.m.Bid notice
Dec 2, 2026Questions due on PennBid by 4 p.m.PennBid listing
Dec 9, 2026Bids due by 2 p.m. and opened at Borough HallBid notice
Dec 21, 2026Act 101 takes effect (60 days after approval)Act text

Sources: borough notices, council agendas, the PennBid listing and the General Assembly, checked November 5, 2026.

Bonds, security and fees

Each bid carries security of 10% of the base bid, and each winner posts two bonds at 100% of the contract

Each bid needs bid security equal to 10% of the base bid, and PennBid asks for a bid bond PDF for every contract a firm bids. The firms that win must furnish a performance bond and a labor and material payment bond, each for 100% of the contract value. PennBid charges awarded bidders 0.33% of the bid amount, with a $100 minimum and a $5,000 maximum, plus tax.

On an example $1,000,000 base bid, bid security is $100,000 and each bond covers the full $1,000,000

$0$250K$500K$750K$1MExample base bidBid security inside: 10%$1,000,000Bid security at 10%Due with the bid$100,000Performance bond at 100%Furnished by the winner$1,000,000Labor and material payment bondFurnished by the winner$1,000,000PennBid fee if awarded0.33%, before tax$3,300 Example base bid$1,000,000Bid security at 10%$100,000Performance bond at 100%$1,000,000Labor and material payment bond$1,000,000PennBid fee if awarded$3,300
Example only, in dollars, applying the notice's percentages to a round base bid. It is no estimate for any of the five contracts. The PennBid fee is before tax. Source: bid notice and PennBid listing, checked November 5, 2026.

What the notice and the PennBid listing require, paraphrased

Bid security
10% of the base bid; a bid bond uploaded as a PDF for each contract bid
Performance bond
100% of the contract value
Labor and material payment bond
100% of the contract value
PennBid fee
0.33% of the bid amount, from $100 up to $5,000 plus tax, charged only to awarded bidders
Pre-bid meeting
Mandatory for every prime bidder, November 9 at 2 p.m., 400 Fayette Street
After the opening
The apparent low bidder and the next two lowest send original executed bid documents to the architect within two business days
Wages
Pennsylvania Prevailing Wage Act; rates set by the Secretary of Labor and Industry
Contract type
Fixed fee contract (PennBid listing)
Award
Made by the borough at a later date; the borough may reject any or all bids or any portion of a bid

The table below applies those percentages to round base bids. The amounts are examples, not estimates for any of the five contracts. The PennBid fee reaches its $5,000 cap at a bid of about $1.52 million.

PennBid's 0.33% fee stops rising at $5,000, which it reaches at a bid of about $1.52 million

$0$1,000$2,000$3,000$4,000$5,000$6,000$0$2M$4M$6M$8MPENNBID FEE IF AWARDEDBASE BID$825$1,650$3,300$5,000 on $3,000,000$5,000 on $8,000,000Cap reached at a bidof about $1.52 million $0$2,000$4,000$6,000$0$2M$4M$6M$8MPENNBID FEE IF AWARDEDBASE BIDCap at about$1.52 million$5,000 cap$3,300
PennBid fee charged to an awarded bidder, in dollars before tax, against the base bid: 0.33% of the bid amount, at least $100 and at most $5,000. Dots mark the example bids in the table below. Source: PennBid listing, checked November 5, 2026.
Example only. Bonding and fees on round base bids under the notice's terms, in dollars. The PennBid fee is before tax.
Example base bidBid security at 10%Performance bond at 100%Payment bond at 100%PennBid fee if awardedFee against the $5,000 cap
$250,000$25,000$250,000$250,000$825
$500,000$50,000$500,000$500,000$1,650
$1,000,000$100,000$1,000,000$1,000,000$3,300
$3,000,000$300,000$3,000,000$3,000,000$5,000
$8,000,000$800,000$8,000,000$8,000,000$5,000

The bar shows each fee against the $5,000 cap. Source: bid notice and PennBid listing. Download the data (CSV)

The apparent low bidder and the next two lowest on each contract must deliver original signed bid documents to the architect within two business days of the opening, which puts the deadline at Friday, December 11, if the opening holds. The borough keeps the right to reject any or all bids, or any portion of a bid.

Prevailing wage and Act 101

Act 101 takes effect December 21, after the December 9 bid opening

The Department of Labor and Industry says prevailing wage applies to construction, reconstruction, demolition, alteration or repair, other than maintenance, done under contract and paid for in whole or part by a public body when the project's estimated total cost is over $25,000. The department's FAQ lists off-site work and material suppliers who do not work at the site among the exclusions.

Act 101 of 2026 narrows that exclusion. The governor approved Senate Bill 908 on October 22, and the act takes effect in 60 days, which falls on December 21, after the bid opening and before any award date the borough has announced. The act adds custom fabrication to the definition of public work and covers workers who fabricate nonstandard goods off site specifically for a public project.

The act names

  • Plumbing and pipe-fitting systems
  • HVAC and refrigeration
  • Sheet metal and duct systems
  • Boiler systems
  • Electrical systems
  • Welding
  • Mechanical insulation
  • Ornamental iron
  • Rebar assembly
  • Signs
  • Whole prefabricated modules

Excluded

  • Structural steel members
  • Precast concrete

Custom fabrication covered by Act 101 of 2026, Senate Bill 908. Source: bill text, Printer's No. 1804, checked November 5, 2026.

Fabrication workers get the prevailing rate for their trade in the county where the project sits, and their employers carry the same reporting duties as any subcontractor. The article on the House vote has the background.

The HVAC, electrical and plumbing primes on this job cover trades the act names.

Whether Act 101 reaches a contract bid before December 21 and signed after it could not be verified from the act or the department's pages.

For bidders

What to settle before December 2

  1. Nov 9

    Put the November 9 site walk and pre-bid meeting on the calendar for every prime you plan to bid. The notice makes attendance mandatory for all prime contract bidders.

  2. Dec 2

    Price your duct, pipe, electrical assemblies or rebar with the shop labor in mind, and submit a question on PennBid before the 4:00 p.m. December 2 deadline asking whether the borough's contract and wage determination will apply Act 101 to custom fabrication on this job. The Bureau of Labor Law Compliance answers project questions at 1-800-932-0665.

  3. Rates

    Labor and Industry also says a public body must request new rates if a contract is not awarded within 120 days of the rate determination date, so check the determination date in the specifications against the borough's award timing.

  4. Surety

    Line up your surety early, since each contract you bid needs its own bid bond.

The public bids guide lists where Conshohocken-area public work is posted, and the prevailing wage guide covers rate determinations and certified payroll.

Caveats

This article draws on the public notice, the PennBid listing and council agendas. The specifications and drawings sit behind a PennBid login and were not reviewed, so the building's size, the construction estimate and the completion date could not be verified. Votes on the October 21 bond ordinance and bid authorization were not in posted minutes on November 5, 2026. Addenda can change the dates or terms, so check the PennBid listing before you submit. For how Act 101 or the bonding terms apply to your firm, ask the borough through PennBid, the Bureau of Labor Law Compliance, your surety or your own attorney.